Procedure

Major construction - New construction, renovation and extension license

Application for a work permit from the City Council that involves a new construction, that involves some structural modification or that involves an increase in the built volume.

OnlineOnline processing available
In-personIn-person care
With costCheck the price

What is this procedure?

Application for a work permit from the City Council that involves a new construction, that involves some structural modification or that involves an increase in the built volume.

Who can apply for it?

Construction companies and individuals

What documentation must be submitted?

Generic:

Proof of the submission of the pre-application for aeronautical easements submitted by the promoter to the State Aviation Safety Agency (AESA) through its website at the following address: aviation security.
Check this out. link to obtain more information about EASA authorizations.

Technical project signed by a competent technician and promoter, preferably endorsed by the corresponding professional association. The project must contain the documentation established in Annex I of Part I of the CTE and must justify all current regulations that must be complied with.
It must also contain the following:
- Specific justification that the project complies with the reservation of spaces intended for parking.

- Justification of compliance with the Ordinance regulating the incorporation of solar energy capture systems in Prat de Llobregat.
The most restrictive parameters established by CTE DB-HE 4, Decree 21/2006 and Ordinance must be met.
To validate the replacement of the solar collection system with an aerothermal one, it is necessary to provide a simulation in HULC comparing the two systems.
Likewise, it is necessary to provide a sheet from the EUROVENT manufacturer with the heat pump's performance and energy efficiency label.

- Justification of compliance with the Ordinance regulating the use of colors, materials and other elements in buildings in Prat de Llobregat.
A chromatic report must be provided that contains the information established in article 19 of the ordinance.

- In the event of installing advertising signs, justification of compliance with the Static Advertising Ordinance of Prat de Llobregat.

- Justification of compliance with Decree 21/2006, of February 14, which regulates the adoption of environmental and eco-efficiency criteria in buildings by providing the supporting document.

- Waste management study with the evaluation of the weight and its nature, providing the supporting document of RD 210/2018.

- Specific graphic justification that the project complies with the applicable urban planning parameters indicating, both in plan and in section, buildable depth, reference point to measure the maximum regulatory height, maximum regulatory height, ground floor level, flight and maximum length of protruding bodies, etc.

- Site plan indicating the width of the sidewalk and the existing urban elements to establish the guarantee that guarantees the repair of possible damage caused to the urban elements of the land as a result of the works, in the terms provided for in art. 16 of the Metropolitan Building Ordinances.

- Plan with proposed use of the public road during the works (location and definition of the construction fence, scaffolding, planned parking reserve, location of waste containers, impact on traffic, etc.) and pedestrian mobility in the event that it is affected.

- Plan with the specifications of the separate sanitation network.

- Specific graphic justification that the project complies with fire prevention regulations, indicating where applicable, both in plan and section, fire sectors, premises and special risk areas, fire resistance of the elements (structure, facades, roof, partition walls, walls, ceilings, doors, etc.), length of evacuation routes, signage of evacuation means, provision of fire protection facilities, etc.

- Basic Health and Safety Study (EBSS) or Health and Safety Study (ESS).
In accordance with Royal Decree 1627/1997, a Health and Safety Study is required if the material execution budget (PEM) (1) is equal to or greater than €313,049 or 500 daily wages (2) or if the duration of the works is greater than 30 working days, employing more than 20 workers simultaneously at any time. In other cases, a Basic Health and Safety Study is required.
(1.) PEM €313,049 = PEC €450,758.73 (13% general expenses 6% industrial profit 21% VAT)
(2.) 500 daily wages = PEM €280,000

Descriptive report, plans and photographs of the affected services with photocopies of the requests to the supply companies for the disconnection or provisional adaptation of the affected services before, during and after the work, if applicable.
Likewise, a photocopy of the requests must be submitted to the supply companies for provisional supplies during the work and definitive supplies once completed, in particular water and electricity.
To carry out trenching or any other intervention in public spaces, the corresponding license must be requested sufficiently in advance to coordinate the work.
If it is necessary to leave any pipes visible, they must be integrated into the architectural composition of the facade.

Justification of compliance with the regulations in force regarding common infrastructures, in particular the building project must comply with Royal Decree 1/1998, of June 27, on common infrastructures in buildings for access to telecommunications services and Royal Decree 346/2011, of March 11, which approves the Regulation regulating common telecommunications infrastructures for access to telecommunications services within the buildings
In addition, the assignment form of a competent technician in the field of telecommunications, endorsed by the corresponding professional association, must be provided, in which he/she assumes the drafting of the project and the control of the installation of common telecommunications infrastructures.

Questionnaire Building and Housing Statistics.

Waste acceptance document signed by an authorized waste manager or written commitment to be provided before starting the works. In accordance with RD 210/2018, this document must include the manager's code, the address of
the work and the amount received as a deposit for subsequent management.
The project must incorporate an assessment of the weight and nature of the waste generated in the work through a justification sheet of the decree.

Declaration from the contractor accepting the execution of the works and photocopy of the Economic Activities Tax (IAE) or the Census of Entrepreneurs, Professionals and Retainers (forms 036 or 037) or written commitment to be provided before starting the works.

Appointment of the competent technician who will assume the management of the works, signed and endorsed by the corresponding professional association.

Appointment of the competent technician who will assume the management of the execution of the works, signed and endorsed by the corresponding professional association.

Appointment of the competent technician who will assume the coordination of health and safety of the works, signed and endorsed by the corresponding professional association if necessary in accordance with RD 1627/1997.

If the works may affect the archaeological site of Les Sorres below a depth of 5 meters from the current level, a
study of the impact that these works could have on the archaeological remains, prepared by a professional specialized in this matter (article 16 of the Special Plan and catalog for the protection of elements of interest of the historical-architectural and environmental heritage of the municipality of El Prat de Llobregat).

If the building or foundation work affects the superficial aquifer (20m) or involves drainage through the extraction of water from the aquifer, a hydrogeological study must be provided defining the construction process of the foundation in relation to the superficial aquifer (shielding techniques, waterproofing, water management, etc.) according to "Agreement of the Catalan Water Agency dated 26 February 2004, (DOGC no. 4093, 17.3.2004)".
Likewise, a copy of the authorization requests must be submitted to the Catalan Water Agency for the extraction of water from the aquifer due to the works, to the Metropolitan Area of ​​Barcelona for the discharge into the network of water from the aquifer due to the works and to the Community of Water Users of the Llobregat Delta for temporary registration during the execution of the works.

If the works involve demolition:

The corresponding demolition license must be requested in advance.

If the works involve any impact on existing urban elements:

Report justifying the need for the intervention and an alternative proposal for the relocation of the altered elements.

If the works for which a license is requested include the construction of an underground car park with two (or more) floors:

Authorization of works in the riverbed police zone in compliance with the Edict of March 3, 2004, on the technical requirements applicable to the authorization of works within the exploitation standards of the aquifers of the Vall Baixa and the Llobregat Delta.

Geotechnical study and hydrogeological study.

Schematic graphs of the forces to which the screens will be subjected in the different execution phases of the emptying of the floors below grade (loads, bending moments, shear and permissible deflections).

Execution project referring to the structure and subsoil of the building, which must explicitly include an annex justifying compliance with the Technical Code (CT) regarding the "DB-SE-C Foundations". The value of the active and passive thrusts to be considered will be that of the CT, taking into account possible redistributions caused by the establishment of fixed anchoring points (Figure 6.6 CT). For the calculation of the aforementioned extremes, especially those referring to deformations, well-known methods will be used, such as those in section F3 of the DB-Foundations; the dimensioning of the screens and the execution method based on the characteristics of the foundations of the neighboring buildings (quality of materials, width, depth, loads, etc.) and the thrusts of the earth and water. If these characteristics cannot be known with sufficient precision, approximations will be adopted, always considering them from the perspective of maximum safety; The minimum thickness of the screen in the second basement must be 0.60m and it must be embedded in a deep layer that is as impermeable as possible and without reaching, in any case, the deep aquifer. This last requirement will be essential for the granting of the license.

Civil liability policy that covers the repair of pathologies, if any, of the buildings affected by the execution of the work and, in any case, with coverage for a minimum amount of 1,500,000 euros.

Sections of the existing adjacent buildings and the projected building.

If applicable:

Project and activity license.

Comply with the technical requirements applicable to the authorization of works within the exploitation standards of the aquifers of the Vall Baixa and the Delta del Llobregat, the Cubeta de Sant Andreu and the Cubeta d'Abrera, included in the agreement of February 26, 2004 of the Board of Directors of the Catalan Water Agency, published in DOGC No. 4093, of 03/17/2004.

ARE Eixample SUD buildings:

Aigües del Prat Waters.

Reserve parking spaces:

In accordance with article 299 of the UNUU of the PGM, in the event of impossibility of fulfilling the reservation of parking spaces in the building and the existence of nearby parking spaces in accordance with the provisions of article 102 of the OME, it will be necessary to justify it in the report. In the event of justifying the exemption from the reservation of spaces in the building itself, it will be necessary to present a deed of purchase or rental contract for a minimum of one year of the spaces required prior to the communication of first occupation. Likewise, it will be necessary to justify that these spaces have not been used for the calculation of the reservation of parking spaces in another building and, in the case of rental, it will be necessary to present a document of acceptance and commitment from the owner for their permanent link according to the model available to the City Council.





































How much does it cost?

Observations

Observations:

Before the start of the work, the executive project of the work, duly approved by the corresponding board, must be presented to the City Council.

For more information:
Department of Urban Planning
c. Major, 2-4 ground floor
Hours:
Monday to Friday, mornings from 9 am to 1:30 pm
Phone: 93.379.00.50

Administrative information

The meaning of administrative silence Positive silence
Resolution time 60 days

Organizations involved in this procedure

Check which organization initiates the procedure, which is responsible for it and which resolves it.

Start

Organization where the procedure is initiated or submitted.

Citizen Information and Assistance Office (OIAC)

Start
LocationPlaza de la Vila 1, 08820, El Prat de Llobregat
Schedule

Mornings, Monday to Friday from 9 a.m. to 1:30 p.m.

Afternoons, from Monday to Thursday from 4.30 pm to 7 pm.

From July 1 to August 31: Mornings, Monday to Friday from 9 a.m. to 2 p.m.

Closed on the afternoons of Maundy Thursday and December 24th and 31st.

Ajuntament del Prat de Llobregat - Principal933790050

Responsible

Organization responsible for managing the procedure.

Department of works and activities licenses

Responsible
LocationCarrer Major, 2-4. 08820 El Prat de Llobregat
Schedule
  • Monday to Friday: 9:00 a.m. to 1:30 p.m. (appointment required for technical assistance)
  • Digital processing support (OAC 360º): Monday to Friday from 8:00 a.m. to 8:00 p.m. for technical questions regarding online submission.
Ajuntament del Prat de Llobregat - Principal933790050