Procedure

Communication of first use and occupation of buildings and facilities

Request made to the City Council to certify that the conditions imposed in the building permit have been complied with.

OnlineOnline processing available
In-personIn-person care
With costCheck the price

What is this procedure?

Request made to the City Council to certify that the conditions imposed in the building permit have been complied with.
Newly constructed buildings or buildings that have been the subject of substantial modification or expansion are subject to this license, when a project has been required for the authorization of the works.

Who can apply for it?

Construction companies or individuals who have previously obtained a building permit.

What documentation must be submitted?

In all cases:

General application form communicating the first use and/or occupation and the return of the corresponding guarantees for the replacement of urban elements. Final work certificate endorsed by the professional association. Execution project of the final state of the work (as built) endorsed by the professional association, in digital format, which includes the modifications made with indication of the material execution budget (PEM), as well as the updated plan of the sewerage network and the plan of the executed foundation. Photocopy of the 900D form of the Declaration of Alteration of Urban Real Estate, duly completed. Certificate issued by the waste management company, referring to the quantities and types of waste delivered. Photograph of the building in digital format. Other documentation specified in the general and specific conditions of the license once the work has been completed.

For multi-family housing buildings, it will also be necessary to provide:

Certificate from the Secretariat of Telecommunications and Information Society certifying that the installation of the common telecommunications infrastructures carried out complies with current legislation. Manual for use and maintenance of the building.


How much does it cost?

This procedure is not free.

Administrative information

The meaning of administrative silence Positive silence
Resolution time 30 days

Organizations involved in this procedure

Check which organization initiates the procedure, which is responsible for it and which resolves it.

Start

Organization where the procedure is initiated or submitted.

Citizen Information and Assistance Office (OIAC)

Start
LocationPlaza de la Vila 1, 08820, El Prat de Llobregat
Schedule

Mornings, Monday to Friday from 9 a.m. to 1:30 p.m.

Afternoons, from Monday to Thursday from 4.30 pm to 7 pm.

From July 1 to August 31: Mornings, Monday to Friday from 9 a.m. to 2 p.m.

Closed on the afternoons of Maundy Thursday and December 24th and 31st.

Ajuntament del Prat de Llobregat - Principal933790050

Responsible

Organization responsible for managing the procedure.

Department of works and activities licenses

Responsible
LocationCarrer Major, 2-4. 08820 El Prat de Llobregat
Schedule
  • Monday to Friday: 9:00 a.m. to 1:30 p.m. (appointment required for technical assistance)
  • Digital processing support (OAC 360º): Monday to Friday from 8:00 a.m. to 8:00 p.m. for technical questions regarding online submission.
Ajuntament del Prat de Llobregat - Principal933790050

Legislation